Legal development

Indonesia Rooftop Solar – Issuance of New Regional Capacity Quotas and Opening of 2024 Capacity Applications

construction of solar farm

    Introduction

    Following the issuance of Minister of Energy and Mineral Resources (MEMR) Regulation No. 2 of 2024 (MEMR 2/2024) earlier this year as the new regulatory framework for captive rooftop solar photovoltaic (PV) systems (Rooftop Solar Systems) in Indonesia, the right to develop new Rooftop Solar Systems will have to comply with the quota system introduced by MEMR 2/2024.

    MEMR 2/2024 mandates every electricity supply company that holds an Electricity Supply Business License for Public Interests (Izin Usaha Penyediaan Tenaga Listrik untuk Kepentingan Umum IUPTLU) and a designated Business Area (Wilayah Usaha) (IUPTLU Holder) to prepare a quota for the development of new Rooftop Solar Systems for each electrical grid within their Business Area, to be submitted to and evaluated by MEMR's Directorate General of Electricity (DGE). The quotas are to be prepared for a 5-year period with an annual (January-December) split.1  

    The implementation of the new quota system comes with the removal of the cap on the maximum installed capacity of the Rooftop Solar Systems (which was set at 100% of the connected power of the relevant customers). MEMR 2/2024 now stipulates that the installed capacity of Rooftop Solar Systems shall be determined based on the required capacity of prospective users (so no more cap) but the approval of such required capacity will depend on the available quota within the relevant grid system.2 

    The requirement to prepare a quota for new Rooftop Solar Systems also applies to PT PLN (Persero) (PLN – the national electricity company) within its national Business Area. To this effect, DGE has recently issued3  Decree No. 279.K/TL.03/DJL.2/2024 (PLN Quota Decree) which stipulates the quota for development of new Rooftop Solar Systems by PLN customers for the period 2024-2028. The PLN Quota Decree stipulates that PLN shall prepare and publish more detailed quotas based on the clustering of their customer service units (e.g. on a regional basis). On 25 June 2024, PLN and MEMR held a virtual socialization event (25 June Socialization) to launch the online-based systems for the implementation of the new Rooftop Solar Systems and PLN issued the available quotas for clustering.

    Please refer to our previous article for a more detailed overview of the key new requirements introduced by MEMR 2/2024.

    Quota for New Rooftop Solar System Development by PLN Customers

    MEMR 2/2024 mandates that the first quota for the period 2024-2028 shall be submitted within 3 months from the promulgation of the regulation, i.e., by 30 April 2024.4  Pursuant to the DGE Decree, PLN submitted its proposed quota per electrical grid to DGE on 25 April 2024.

    Based on DGE's evaluation of PLN's submission, the following quotas for 2024-2028 have been set by DGE:

    Electrical Grid System/Province

    Quota for Rooftop Solar Systems (MW)

    2023

     2025

     2026

     2027

     2028

     Sumatra 35.0 45.0 60.0 70.0 80.0
     West Kalimantan  7.1 9.8 16.4 17.2 18.5
     Kalseltengtim (South, Southeast and East Kalimantan) 22.1 34.0 58.7 62.8 68.3
     North Kalimantan 0.81.11.9 2.0 2.2 
     Java-Madura-Bali 825.0 900.0 910.0 1,010.0 1,400.0
     Sulutgo (North Sulawesi and Gorontalo) 0.2 0.4 0.6 0.8 1.0
     Sulbagsel (Southern Sulawesi Region) 8.0 10.0 12.0 14.0 16.0
     Maluku and North Maluku 0.7 1.0 1.21.4 1.7 
     Papua and West Papua 0.8 1.11.31.61.9
     West Nusa Tenggara 0.9 1.21.5 1.8 2.2 
     East Nusa Tenggara 0.6 0.70.9 1.1 1.3 
     TOTAL 901 1,004 1,065 1,183 1,593

    It should be noted that the stipulated quota appears to be increasing each year, with the highest allocation going to the Java-Madura-Bali region, followed by Sumatra. This gradual increase aligns with statements made by MEMR and PLN that the quota approach is implemented due to the intermittent nature of grid-tied Rooftop Solar Systems, which necessitates a gradual ramp-up of rooftop solar installed capacity through grid quotas to ensure grid stability and reliability until flexible smart-grid infrastructure is developed by PLN.

    Next Steps: Application and Allocation

    Pursuant to MEMR 2/2024, based on DGE's quota stipulation, each IUPTLU Holder (including PLN) shall prepare quotas based on the clustering of their customer service units. The clustering of quotas shall then be reported to DGE and published by the respective IUPTLU Holders on their website, app and/or social media platforms within 10 business days of the quota stipulation by DGE.5 

    In accordance with this requirement of MEMR 2/2024, the clustering of quotas for the year 2024 has been announced by PLN on 25 June 2024, as follows:

    Electrical Grid System/Province

    Cluster

     Stipulated Quota (Watt)

    Quota of the Existing Projects in 2024 (Watt)

     Available Quota for 2024 (Watt)

     Operation Construction
    SumatraAceh 2,405,330 21,000 - 2,384,330
    North Sumatra 12,264,498 1,952,500 11,540,700 (1,228,702)6 
    West Sumatra 2,880,999 - - 2,880,999
    Bangka Belitung 1,531,325 154,300 - 1,377,025
    Riau and Riau Islands 4,899,839 - 4,000 4,895,839
    Lampung  4,523,769 220,000 2,160,700 2,143,069
    S2JB (South Sumatra, Jambi and Bengkulu) 6,755,577 37,180 910,590 5,807,807
    West Kalimantan - 7,083,789 50,700 - 7,033,089
    Kalseltengtim (South, Central and East Kalimantan)South and Central Kalimantan 12,215,917 - - 12,215,917
    East Kalimantan 10,700,293 7,000 529,700 10,163,593
    Java-Madura-BaliBanten 148,986,993 1,793,660 32,805,390 114,387,943
    Greater Jakarta Area 133,407,330 5,797,335 8,708,890 118,901,105
    West Java 224,305,904 24,124,755 112,283,050 87,898,099
    Central Java and DIY 109,883,066 7,625,920 25,419,670 76,837,476
    East Java 178,495,499 1,604,437 17,734,410 159,156,652
    Bali 29,921,210 589,340 2,739,680 26,592,190
    Sulutgo (North Sulawesi and Gorontalo)North Sulawesi, Central Sulawesi and Gorontalo 199,999 - - 199,999
    Sulbagsel (Southern Sulawesi Region)South Sulawesi, Southeast Sulawesi and West Sulawesi 8,000,000 55,000 5,010,100 2,934,900
    Maluku and North Maluku - 720,002 25,000 - 695,002
    Papua and West Papua - 809,999 82,500 - 727,499
    West Nusa Tenggara - 930,000 10,800 36,000 883,200
    East Nusa Tenggara - 550,000 - - 550,000

    Based on the clustering of quotas published by PLN, it appears that PLN has also accounted for the capacity quotas approved and granted to customers before the implementation of the new Rooftop Solar System mechanism. Therefore, the remaining quota per cluster available for the rest of the year has been reduced by the approved capacity quotas. This results in certain clusters having quite significantly reduced available quotas (e.g., West Java and Southern Sulawesi Region). In the case of the North Sumatra cluster, this even resulted in a negative figure for the available quota. It remains to be seen whether the negative figure means there will be no available quota, for the North Sumatra cluster for the remainder of 2024.

    Following the publication of the quotas per cluster, prospective customers will then be able to submit applications to procure and install Rooftop Solar Systems. Pursuant again to MEMR Regulation 2/2024, the first applications following the issuance of the relevant quota decree must be submitted within 1 month from the publication of the initial quota by the relevant IUPTLU Holder (such as PLN). Subsequent applications should also be submitted strictly during the bi-annual application windows, i.e. in January and July.7  In this respect, PLN has confirmed during the 25 June Socialization that the applications for the 2024 quotas will be opened on 1 July 2024 and to be submitted through PLN's mobile app, "PLN Mobile".

    In terms of allocation of the quota, although MEMR Regulation 2/2024 does not detail the principles governing quota determination, MEMR and PLN clarified during the 25 June Socialization that: 

    • quotas will be allocated on a first-come-first-served basis;
    • if a customer's submitted quota is rejected, the quota will become available again; and
    • if an application is rejected due to the unavailability of a remaining quota, the prospective customer will be placed on a waiting list to be processed in the next period when the quota for the relevant cluster becomes available.8

    It is also worth noting that once a customer is allocated a quota, they must obtain the operational worthiness certificate (SLO, required for COD) for the Rooftop Solar System within 6 months from the approval date, otherwise the quota approval will be revoked.9  Furthermore, if there are any remaining quotas for the development of Rooftop Solar Systems in any given cluster at the end of the current year, these remaining quotas will be added to the development quotas of that cluster for the following year.10 

    Based on the information conveyed during the June 25 Socialization, the following process applies to submit an application for quota allocation through the PLN Mobile app:

    1. applicants must first create an ID directly on the app;
    2. applicants should then access the "PV Rooftop" menu to submit their application for Rooftop Solar Systems approval by entering the proposed quota and upload the required administrative and technical documents;
    3. if the quota is unavailable, the application cannot be submitted;
    4. once successfully submitted, PLN will notify the applicant within 7 calendar days if the application can proceed based on the initially submitted documentation;
    5. if the application is rejected, the quota becomes available again and, if the application can be processed for verification, PLN will issue a final decision on approval or rejection within 30 calendar days from the initial submission date.

    Given the finite nature of the proposed quota approach, PLN grid-connected customers (both commercial & industrial as well as residential) who desire to procure all or part of their electricity needs from Rooftop Solar Systems as well as the rooftop solar market developers and other business participants, will be closely monitoring the clustering quotas and how these get allocated by PLN in practice. Interested parties will be holding their breath hoping that the desired capacity for their projects remains available when submitting their application as they would otherwise have to wait for the opening of the next application window (i.e. 5 months later).

    It will have to be seen if the app-based system is sufficiently reliable and secure, and that the required transparency over the allocation of new capacity per grid system on a first-come first-served basis (which is of paramount importance to instill market confidence) is ensured in practice throughout PLN's vast service area.

    Authors: Frédéric Draps, Partner / Foreign Legal Consultant; and Khairunissa Yuliandhini, Associate.

    1. Articles 7 and 8 of MEMR 2/2024.
    2. Article 12 of MEMR 2/2024.
    3. On 27 May 2024.
    4. Article 8(3) and (4) of MEMR 2/2024.
    5. Article 9 of MEMR 2/2024.
    6. The total capacity quota granted to projects that are in operation and in construction in 2024 within the North Sumatra cluster has already exceeded the stipulated quota. 
    7. Article 14 of MEMR 2/2024.
    8. Article 15(8) of MEMR 2/2024.
    9. Article 26 of MEMR 2/2024.
    10. Article 11 of MEMR 2/2024.

    Oentoeng Suria & Partners (OSP) is an Indonesian firm affiliated with Ashurst, a global law firm.  The Ashurst Group comprises Ashurst LLP, Ashurst Australia and their respective affiliates (including independent local partnerships, companies or other entities) which are authorised to use the name "Ashurst" or describe themselves as being affiliated with Ashurst, such as OSP.  Some members of the Ashurst Group are limited liability entities. Information about OSP can be found in www.oentoengsuria.com, and further information on which Ashurst Group entity operates in any country can be found on our website at www.ashurst.com

    This material is current as at 2 July 2024 but does not take into account any developments to the law after that date. It is not intended to be a comprehensive review of all developments in the law and in practice, or to cover all aspects of those referred to, and does not constitute legal advice. The information provided is general in nature, and does not take into account and is not intended to apply to any specific issues or circumstances. Readers should take independent legal advice. No part of this publication may be reproduced by any process without prior written permission from Ashurst. While we use reasonable skill and care in the preparation of this material, we accept no liability for use of and reliance upon it by any person.

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.

    image

    Stay ahead with our business insights, updates and podcasts

    Sign-up to select your areas of interest

    Sign-up